The stages every kit calendar is built from
A kit order is a chain of fixed stages, and the order-by date for any season is simply those stages added together and counted back from the day the kit must be on bodies. The figures below are the ones ZipaSports publishes and quotes against; they do not change by sport.
| Stage | Published time | Calendar equivalent | Who controls it |
|---|---|---|---|
| Free digital mockup | Within 24 hours of the brief | 1 day | Factory studio |
| Mockup revisions and approval | Unlimited revisions, no fixed time | Usually 2–5 days in practice, depending on how quickly your committee answers | Buyer |
| Physical sample (optional) | 5–7 days production, charged at sample cost and credited against bulk | 1 week, plus 5–10 days courier to reach you | Factory, then courier |
| Bulk production, standard | 15–25 business days after design approval | 3–5 weeks | Factory |
| Bulk production, express | 7–12 days, at additional cost | 1–2 weeks | Factory |
| Air courier (DHL, FedEx, UPS) | 5–10 days worldwide | 1–1.5 weeks | Courier and customs |
| Sea freight (large orders) | 3–6 weeks | 1–1.5 months | Forwarder and port |
Two things on that table are yours to shorten: how fast the mockup is approved and how fast the size sheet, names and numbers arrive. Production cannot start until both are in.
Three planning totals: with a sample, without, and express
Adding the stages gives three totals worth memorising, measured from the day you send the brief to the day the courier delivers.
- Standard, no physical sample: one day for the mockup, a few days of revisions, 15–25 business days of production and 5–10 days of courier. Plan on about seven weeks; five is possible when approval is quick and production runs at the short end.
- Standard with a physical sample: the same chain plus 5–7 days to make the sample and 5–10 days to courier it to you before you approve. Plan on ten to twelve weeks. Brands launching a first collection and clubs changing fabric or fit should take this route.
- Express, no sample: mockup, revisions, 7–12 days of production and 5–10 days of courier. Plan on three weeks, and treat it as the rescue path rather than the default.
Business days matter here. Twenty-five business days is five working weeks, not twenty-five calendar days, and public holidays at either end add to it. ZipaSports counts production from design approval with a complete size sheet in hand, and the factory's WhatsApp reply within 2 hours in business hours and email reply within 24 hours are part of keeping the approval loop short. The shipping policy page shows the same chain by destination.
Order-by calendar for every sport and season
The table applies the three totals to the seasons buyers plan around. Months are typical for the northern hemisphere unless stated; count back from the first date the kit is worn, not the official season start.
| Sport or setting | Kit usually needed by | Brief in by (with sample, 10–12 weeks) | Brief in by (no sample, about 7 weeks) | Express last resort (about 3 weeks) |
|---|---|---|---|---|
| Football pre-season | July friendlies, August league | Late April | Late May | Late June |
| Cricket (UK spring) | April | January | Mid-February | Early March |
| Cricket (Australia summer) | October | July | Mid-August | Early September |
| Rugby autumn start | September | June | Mid-July | Early August |
| Basketball winter league | October to November | July to August | Late August to September | Late September |
| School PE kit (UK, USA, Canada, Europe) | September term | June | Mid-July | Early August |
| School PE kit (Australia) | Late January | October | Late November | Early January |
| Dance show and recital season | Show date, often May to July | 12 weeks before | 7 weeks before | 3 weeks before |
| Cheer and dance competition season | First competition, often winter to spring | 12 weeks before | 7 weeks before | 3 weeks before |
| MX race season | Round one, often spring | 12 weeks before | 7 weeks before | 3 weeks before |
| Company sports day or charity run | Event date | 12 weeks before | 7 weeks before | 3 weeks before |
Worked example: a football club planning for a mid-August kick-off
Take a club whose first league fixture is on 15 August and which wants kit on players for the final friendly a week earlier, on 8 August. That is the anchor date, and everything counts back from it.
- Delivery needed by 8 August. Courier is 5–10 days, so the order must leave Sialkot by about 29 July.
- Standard production is 15–25 business days, so design approval with a full size sheet must be in by 24 June to be safe at the long end.
- Mockup revisions usually take a week of committee time, so the brief with crest, colours and sponsor logos should go in by mid-June.
- If the club also wants a physical sample to check a new fabric weight, add 5–7 days to make it and 5–10 days to receive it, which pulls the brief back to early May.
The club that briefs in mid-June and approves in a week still has slack, because production may finish nearer 15 business days than 25. The club that briefs in mid-July has no slack and is now an express order at 7–12 days production plus courier. The football club page lists what the size sheet, names and numbers list and sponsor files should contain so approval is not what slows the chain.
Worked example: a school or academy September intake
Schools and academies face a problem clubs do not: the size sheet depends on pupils who have not arrived yet. September kit for a new intake cannot be measured in June because the children are still at their previous school. The usual answer is to split the order in two.
The first order covers returning year groups, whose sizes are known, and it follows the standard calendar: brief by June, approval before the summer break, production through July, courier in early August. The second order covers the new intake and is briefed the moment sizing is done in the first week of term, as a repeat of the same design with a new size breakdown. Because the artwork, grading and colours are already on file, the second run needs no new mockup cycle and goes straight to production, arriving in late September or early October on standard timing or sooner on express.
Academies with rolling intakes across the year use the same repeat mechanism every term. ZipaSports keeps approved designs on file for exactly this purpose, and repeat runs below the 20–25 piece minimum are possible on request for established academies. The academy kit guide and school sports uniform guide cover sizing days and roster sheets in detail.
Reversed seasons: Australia, New Zealand and southern-hemisphere buyers
Buyers in Australia and New Zealand run the same sports on the opposite calendar, and the planning maths does not change, only the months. Cricket is a summer sport starting around October, so the brief goes in during July; winter football codes start around March or April, so the brief goes in over the Christmas period, which means allowing for factory and courier holidays at both ends.
Courier timing to Australia sits inside the same 5–10 day window ZipaSports quotes worldwide, so a Sydney club and a Manchester club count back the same number of days from their respective season starts. What differs is the size of the order: state associations and multi-team clubs ordering several hundred pieces sometimes choose sea freight at 3–6 weeks for the bulk and send a small first tranche by air for early-season fixtures.
| Setting | Northern hemisphere | Southern hemisphere |
|---|---|---|
| Football season start | August | March to April |
| Cricket season start | April | October |
| Rugby season start | September | February to March |
| School year start | September | Late January to February |
| Holiday period to plan around | Late December | Late December to January |
The Australia page covers import and sizing conventions for that market.
Event-driven seasons: dance shows, cheer competitions and MX rounds
A league start can tolerate a week's slip because early fixtures can be played in last season's kit. A dance show, a cheer competition or the first MX round cannot, because the date is fixed by someone else. Plan these orders as if the event were a week earlier.
Dance studios and cheer programmes also carry the most design risk in the chain. Costumes with rhinestone or crystal work, sequin panels or mesh overlays take longer to finalise at mockup stage because there are more decisions, and a physical sample is advisable when a new base fabric or embellishment is used for the first time. Studios should plan on the 10–12 week total and brief straight after casting. The costumes and rhinestone and crystal pages describe what is decided at mockup.
MX and enduro teams have a different pattern: rider names, numbers and sponsor decks are usually confirmed late, after sponsorship agreements close. Send the jersey and pants design for the 24-hour mockup early, then treat sponsor logos as a final revision. Production at ZipaSports does not start until artwork is approved, so a team that locks the base design and adds logos in one late revision keeps its place in the calendar without a second mockup cycle.
What moves the date, and how to protect it
The production clock at ZipaSports starts on design approval with a complete size sheet, names and numbers list and confirmed quantities. It pauses when any of those is missing, so assemble those files before the mockup is approved rather than after.
- Size sheet: pieces per cut and size, collected on one sheet. Late additions after cutting has started become a second order.
- Names and numbers: a typed list matched to sizes. A spelling change after printing is a remake at the buyer's cost; a misprint against the approved list is covered by the guarantee.
- Artwork: vector logos and Pantone references at the first brief.
- Staggered dispatch: where a squad needs match kit first and training wear later, ask for the match kit to ship first and the rest to follow.
Build a week of buffer into every plan for one more reason. Quality Guarantee: if any garment arrives with a manufacturing defect, we remake it free of charge — the remake goes into production within 3 days of your report. That buffer is what lets a remake arrive before the first fixture rather than after it. The Quality Guarantee page carries the full terms and claim steps.
Frequently Asked Questions
When should a football club order kit for the new season?
Brief the factory by mid to late May for an August start if no physical sample is needed, or by late April to early May if you want a sample first. That allows the 24-hour mockup, a week of revisions, 15–25 business days of production and 5–10 days by courier, with a week of buffer before the first friendly.
How long before the cricket season should we order shirts and whites?
Cricket kit should be briefed to the factory about seven weeks before the first match without a physical sample, or ten to twelve weeks with one. For a UK April start that means briefing in mid-February or January; for an Australian October start, mid-August or July. Coloured and white kit can run as separate designs in the same order.
Can we still get kit if the season starts in three weeks?
Kit for a season starting in three weeks is usually still possible on express production. ZipaSports runs express at 7–12 days after approval at additional cost, followed by 5–10 days by DHL, FedEx or UPS, so a clean brief approved within a day or two can be on players in about three weeks. There is no time for a physical sample on that path.
Are lead times longer in peak season?
The published windows of 15–25 business days standard and 7–12 days express are what ZipaSports quotes against all year, and the quote confirms the production slot before you approve. Buyers protect themselves by briefing on the calendar above rather than at the last minute, when every club in the league is ordering at once.
What is the difference between business days and calendar days in the lead time?
Production is quoted in business days, so 15–25 business days is three to five working weeks, longer if public holidays fall inside it. Courier times of 5–10 days are calendar days including transit and customs clearance. Always convert both to a date on your own calendar when planning.
Should we skip the physical sample to save time?
Skip the physical sample when the design is a repeat, a colour change on a fabric you already wear, or a standard sublimated jersey on the factory's size chart. Keep it when you are changing fabric, fit or embellishment, launching a brand, or ordering several hundred pieces, because a sample in 5–7 days is cheaper than a wrong run.
Does shipping to Australia or Canada take longer than to the UK?
ZipaSports quotes the same 5–10 day courier window worldwide for DHL, FedEx and UPS, so Australia, Canada, the USA, the UK and Europe are planned on the same count. Customs clearance is the variable, which is why the upper end of the window is the one to plan on.
Can the match kit ship before the training wear?
Match kit can be produced and dispatched ahead of the training wear on request. Ask at order stage for the match kit to go first, with tracksuits, training tops and bags following in a second consignment. Each consignment carries its own courier time, so the second one still needs to be planned against the date it is actually needed.
What happens if kit arrives with a defect a week before the first game?
Send photos and your order reference on WhatsApp or email within 7 days of delivery. ZipaSports confirms within 24 hours in business hours, puts the remake of the affected pieces into production within 3 days and ships them at no charge. A week of buffer in your plan is what makes that remake arrive in time.
How early can we brief if we do not have final sizes yet?
You can brief the factory before final sizes exist. The 24-hour mockup, revisions and approval of the artwork can all happen before the size sheet is ready, so a club or school can lock the design in spring and add sizes after a sizing day. Production starts when the size sheet and names list arrive.